The clean-energy transition isn't waiting on a breakthrough. It's waiting on specific, named chokepoints — one per project. This is the register of exactly where each project stalls, and why.

The stall register

Where each project stops
and why.

Every entry below comes from its project's own feasibility analysis — the physical, legal, or logistical chokepoint the engineers themselves flagged. Patterns repeat: environmental litigation, supply-chain crunches, grid power that doesn't exist yet, and the US military's schedule. Click any project name for its full page.

Group 01 · 15 entries

Mega ports

Fifteen deepwater super-ports, each dredged to a 24-meter clearance. The recurring stalls: winter, silt, steel, and sharing harbors with the Navy.

North Atlantic Gateway

Penobscot Bay, Maine
Stalled at: dredging through winter. Sub-arctic Atlantic weather and freezing seas shut down conventional dredging for months, and carving the 24-meter clearance through Penobscot Bay's rocky bathymetry means extensive underwater bedrock blasting — which invites severe environmental delays. Jurisdiction: dredging and blasting in Penobscot Bay need a federal permit from the U.S. Army Corps of Engineers, New England District (Clean Water Act §404 / Rivers and Harbors Act §10), §401 water-quality certification from the Maine Department of Environmental Protection, and underwater blasting in whale habitat triggers consultation with NOAA Fisheries under the Marine Mammal Protection Act.

New York / Newark Super-Complex

New York Harbor · offshore podiums
Stalled at: building inside the world's busiest harbor. Constructing offshore terminal podiums and dredging 24-meter channels in one of Earth's most congested navigation zones risks immense vessel-traffic gridlock — every construction barge competes with the container ships the port exists to serve.

Delaware Bay Megacity Interface

Delaware Bay / Cape May
Stalled at: getting bulk cargo inland. The port's purpose is pumping massive volumes of raw industrial aggregates to interior foundries, but moving that tonnage by truck would overload regional roads — the project only works if its high-speed rail cargo link is built in parallel.

Hampton Roads Sovereign Anchorage

Hampton Roads, Virginia
Stalled at: sharing the harbor with the Navy. Co-locating high-volume automated commercial container operations alongside active military defense shipyards creates severe scheduling friction and security-clearance bottlenecks — warships and box ships don't queue well together.

South Atlantic Core

Savannah / Charleston intersect
Stalled at: the mud. Silt build-up and shallow river-estuary topography mean a 24-meter channel would constantly refill — a permanent, never-finished dredging treadmill rather than a one-time dig.

Mississippi Delta Super-Hub

Plaquemines Parish, Louisiana
Stalled at: the next hurricane. Storm surges threaten to inundate the low-lying terminal yards, so the port's survival is chained to the MSD-11 subterranean retention-vault project being completed first — no vaults, no port.

Texas Star Maritime Vertex

Galveston / Houston deepwater spit
Stalled at: steel supply. The specialized corrosion-resistant alloy steel for heavy chemical docking berths is an acute supply-chain bottleneck — the berths can't be built until domestic foundries retool to produce it.

West Florida Logistics Anchor

Tampa Bay, Florida
Stalled at: the bay floor. Shallow waters over limestone bedrock make traditional dredging exceptionally slow and costly, and extensive dredging threatens the delicate coastal bay ecosystems the region depends on. Jurisdiction: dredging Tampa Bay requires a U.S. Army Corps of Engineers, Jacksonville District permit (§404/§10) with §401 certification from the Florida Department of Environmental Protection, and seagrass and mangrove impacts trigger Endangered Species Act consultation with the U.S. Fish and Wildlife Service.

Straits of Florida Terminus

Miami offshore grid
Stalled at: the open ocean. Atlantic swells in the exposed Straits of Florida can destabilize both construction and container loading — the terminal only becomes viable behind the MIA-9 offshore breakwater, which has to be built first.

Puget Sound Super-Terminal

Anacortes / Bellingham, Washington
Stalled at: the courtroom. Environmental litigation over disruption to Puget Sound marine life threatens multi-year construction delays before a single pylon is driven. Jurisdiction: every pylon needs a U.S. Army Corps of Engineers, Seattle District permit, §401 certification from the Washington State Department of Ecology, and Endangered Species Act §7 consultation with NOAA Fisheries for Southern Resident orcas and Puget Sound Chinook — any one of these is a standing invitation to the lawsuits flagged above.

Columbia River Deepwater Spur

Astoria, Oregon
Stalled at: the bar. The Columbia River Bar's crushing waves and shifting sandbars create continuous depth instability — the 24-meter channel won't stay dredged without permanent underwater stabilization, tied to the AST-21 tidal gate.

Golden Gate Logistics Wall

Richmond / Oakland, California
Stalled at: the power bill. An all-electric, zero-emission automated crane matrix draws so much electricity it risks overloading the regional municipal grid — the port needs its own dedicated SMR microgrid power supply first.

Southern California Absolute Hub

LAX / Long Beach consolidated podium
Stalled at: the container yard. Processing tens of millions of TEUs across 45 berths creates an extreme physical staging bottleneck — containers pile up faster than any surface yard can clear them, forcing the whole design toward direct ship-to-rail transfer within minutes of docking.

San Diego Sovereign Frontier

San Diego, California
Stalled at: the border. High security risks and smuggling exposure along the southern frontier turn every container into a customs-inspection bottleneck that automation alone can't fully clear. Jurisdiction: container screening is run by U.S. Customs and Border Protection's Office of Field Operations — inspection throughput is set by federal staffing and screening protocol, not by the port's own automation.

Alaskan Sovereign Link

Seward, Alaska
Stalled at: the cold itself. Sub-zero temperatures embrittle structural steel and freeze the hydraulics of automated gantry cranes — the port needs arctic-grade alloys and internally heated systems before it can operate a single winter.
Group 02 · 25 entries

Coastal defense & water

Twenty-five storm-surge barriers, tidal gates, and aqueducts. The recurring stalls: the ground won't cooperate, the water table fights back, and the power has to come from somewhere.

Atlantic Coast

BOS-1 · Boston Harbor Barrier Island Ring

Winthrop to Hull, Massachusetts
Stalled at: staging. The harbor's shallow draft actually favors the engineering, but there is nowhere to stage 16 million tons of concrete and armor stone inside Boston's dense urban grid — the project hinges on off-site deepwater staging and ocean-side barge delivery.

NYC-2 · New York / Newark Bight Tidal Sluice Gate

Sandy Hook to Rockaway, New York
Stalled at: tides versus traffic. Structurally feasible, but extreme tidal forces combined with the heaviest commercial vessel traffic on Earth turn the construction corridor into a severe logistical knot.

LIS-3 · Long Island Sound East-End Ingress Block

Orient Point to Plum Island, New York
Stalled at: the weather window. Deepwater pylon placement is feasible, but North Atlantic storm volatility keeps stalling barge deployments — construction can only proceed inside verified calm-weather windows.

DEL-4 · Delaware Bay Surge Absorption Cavern Array

Cape May Peninsula, New Jersey
Stalled at: the water table. Excavating 50-meter-deep surge caverns in coastal groundwater risks saltwater flooding the dig itself — the project depends on cryogenic ground-freezing to hold the water back while the chambers are bored and lined.

CHB-5 · Chesapeake Bay Gateway Lock Network

Mouth of Chesapeake Bay, Virginia
Stalled at: the Navy. The bay mouth can't be closed to traffic during construction because Hampton Roads shipyards need military vessels moving at all times — the lock network must be built around an always-open defense lane.

OBX-6 · Outer Banks Armored Dune Spine

Outer Banks, North Carolina
Stalled at: the sand. Driving interlocking carbon-fiber sheets 30 meters deep through shifting barrier-island sand runs into severe sheet-alignment and subterranean-friction problems — the ground itself fights the installation.

CHS-7 · Charleston Peninsula Marine Podium Lift

Charleston, South Carolina
Stalled at: the historic district. Hydraulically jacking an entire living, occupied historic city onto a concrete podium without cracking centuries-old masonry is the whole project — one wrong lift and irreplaceable heritage architecture is gone. Jurisdiction: work in a historic district triggers National Historic Preservation Act §106 review — the Advisory Council on Historic Preservation, the South Carolina State Historic Preservation Office, and the City of Charleston's Board of Architectural Review each get a binding say, and any of them can stop the lift.

SAV-8 · Savannah River Tidal Isolation Sluice

Mouth of the Savannah River, Georgia
Stalled at: the current. Peak tidal currents are too violent to safely drop and weld 800,000 tons of vertical lift gates — the river has to be temporarily tamed with inflatable coffer dams before the steel can go in.

MIA-9 · South Florida Coral-Reef Kinetic Breakwater

150 miles of coastline, Miami to the Keys
Stalled at: the concrete plant. A 150-mile offshore reef matrix needs 25 million tons of eco-concrete — an unprecedented production run that chokes on the onshore supply chain before a single block is laid.

JAX-10 · Jacksonville St. Johns River Surge Diverter

St. Johns River, Jacksonville, Florida
Stalled at: the tunnel face. Running four tunnel-boring machines simultaneously beneath a major urban river carries high risk of subterranean collapse or water-table intrusion mid-bore.
Gulf Coast

MSD-11 · Mississippi River Delta Retention Vault Matrix

Plaquemines Parish, Louisiana
Stalled at: the mud. Excavating ten 500-meter-wide, 60-meter-deep caverns in hyper-saturated delta soil is the single hardest geotechnical dig in the set — the walls want to collapse the moment they're opened, so the retaining walls must be built before the digging starts.

GAL-12 · Galveston Bay Coastal Defense Wall

30-mile perimeter, Galveston Bay, Texas
Stalled at: the estuary. A 30-mile solid wall across the bay would strangle natural tidal exchange and wreck the enclosed estuary's ecology — the wall only works with hundreds of auto-closing culverts engineered into its base. Jurisdiction: walling off the bay needs a U.S. Army Corps of Engineers, Galveston District permit with §401 certification from the Texas Commission on Environmental Quality, plus ESA consultation with NOAA Fisheries and the U.S. Fish and Wildlife Service for the estuary species the wall would strand.

MOB-13 · Mobile Bay Estuary Tidal Sluice

Mobile Bay, Alabama
Stalled at: the steel mill. 1.2 million tons of specialized structural steel has to be sourced while every other project in the national program is competing for the same foundry output.

TPA-14 · Tampa Bay Marine Barrier Ring

Tampa Bay, Florida
Stalled at: the alignment. Spanning the wide, open bay entrance means aligning massive concrete elements to millimeter precision across miles of open ocean — a surveying problem as much as a construction one.

MSY-15 · New Orleans Interior Drainage Super-Pump Grid

New Orleans, Louisiana
Stalled at: the blackout. Conventional pump stations die with the municipal grid in every major hurricane — the 40 giant axial pumps are useless unless their dedicated subterranean SMR power units are built first.

SAB-16 · Sabine Pass Industrial Sluice Shield

Texas–Louisiana border
Stalled at: the refineries. The pass is ringed by volatile energy infrastructure, so standard explosive excavation is off the table — the deepwater gate housings have to be carved out with zero-vibration directional boring.

ATC-17 · Atchafalaya Basin Delta Land-Builder System

Atchafalaya Basin, Louisiana
Stalled at: the habitat. Forcing rapid silt deposition across 500,000 acres risks choking the aquatic wildlife habitats the system is meant to protect — every diversion channel has to be threaded around threatened and endangered species zones. Jurisdiction: every channel through wetlands needs a U.S. Army Corps of Engineers, New Orleans District §404 permit and ESA §7 consultation with the U.S. Fish and Wildlife Service — the threatened-species zones named here are exactly what that consultation exists to protect.

CRP-18 · Corpus Christi Deepwater Ingress Gate

Corpus Christi Ship Channel, Texas
Stalled at: the pressure seals. Dropping hydraulic gates to 24-meter depth pushes standard seal engineering past its limits — the seals have to be reinvented in ultra-dense rare-earth alloys before the gates can go in.

LGM-19 · South Texas Lago-Madre Retention Matrix

Laguna Madre, Texas
Stalled at: the earthmoving bill. Carving the basin network means moving 35 million cubic meters of earth — so fuel- and labor-intensive that it breaks standard construction timelines and demands round-the-clock cooperative crews.
Pacific & Interior

SFO-20 · Golden Gate Tidal Sluice and Lock System

Golden Gate Strait, California
Stalled at: the strait. Extreme depth and violent currents make anchoring 18 million cubic meters of concrete a dangerous, turbulent operation — the plan depends on floating massive pre-cast shells into pre-dredged slots instead of pouring in place.

AST-21 · Columbia River Deepwater Tidal Gate

Astoria, Oregon
Stalled at: the river itself. You can't just dam the Columbia to build the gates — halting its immense outflow would flood everything upstream — so a temporary subterranean bypass channel has to be bored first, then sealed.

SEA-22 · Puget Sound Multi-Node Isolation Grid

Puget Sound, Washington
Stalled at: the orcas. Endangered orca and salmon populations mean the three tidal blockades can't be solid walls — each must be engineered as an elevated eco-viaduct with continuous underwater wildlife corridors running beneath it. Jurisdiction: the eco-viaduct design isn't optional — ESA §7 consultation with NOAA Fisheries (Southern Resident killer whales, listed salmon runs) is mandatory, any U.S. Army Corps of Engineers, Seattle District permit will carry those wildlife-corridor conditions, and the Washington State Department of Ecology holds §401 certification leverage over the whole thing.

SAC-23 · Sacramento–San Joaquin Delta Aqueduct Super-Siphon

150-mile subterranean network, California
Stalled at: the fault lines. Boring 150 miles of tunnel through California's active seismic zones risks catastrophic collapse in a major quake — the entire aqueduct needs bedrock-anchored seismic isolation engineered in from the start.

SLT-24 · Imperial Valley Salton Sea Inversion Aqueduct

400 miles of pipeline, Southern California
Stalled at: the power cord. Pumping heavy water volumes 400 miles inland to refill the Salton Sea demands a continuous energy load no standard grid can carry — the pumps wait on dedicated SMR microgrid and solar capacity at the retrofitted hub airports.

GLC-25 · Mid-Continental Great Lakes Control Grid

Great Lakes basin
Stalled at: the coordination problem. Five lakes, multiple canals, one stable water level — no human operator can balance it, so the entire grid waits on its automated central control matrix working flawlessly across every gate at once.
Group 03 · 1 entry

High-speed rail

Seventeen thousand miles of automated maglev, built in five years across 75 simultaneous fronts.

17,000-Mile Automated Maglev Network

National · 75 civil infrastructure sectors
Stalled at: the timeline, not the technology. Building 17,000 miles sequentially would take decades — the stall is steel and maglev-component supply shortages plus environmental litigation over every mile of new corridor. Jurisdiction: every mile of new line needs a construction certificate from the Surface Transportation Board (49 U.S.C. §10901), and the STB's Office of Environmental Analysis must complete NEPA review — an EA or a full EIS — before a single rail is laid, with the Federal Railroad Administration typically serving as a lead federal agency; each affected state's DOT and public utilities commission then adds its own permitting layer. The program's answer is 75 simultaneous construction fronts, which is itself the hardest part to actually staff and supply.
Group 04 · 2 entries

Energy & minerals

The power and the raw materials everything else depends on.

503 Subterranean Gen-IV SMR Microgrids

503 commercial airports, nationwide
Stalled at: the reactor itself. Traditional reactors can't scale to 503 units — meltdown risk and massive water-cooling demands make it unfeasible — so the entire program waits on helium-cooled TRISO pebble-bed Gen-IV designs that physically cannot melt down, plus a gravity-fed emergency cooling system that needs zero human intervention. Jurisdiction: no unit gets built until the Nuclear Regulatory Commission's Office of Nuclear Reactor Regulation licenses the design — TRISO pebble-bed concepts are still working through NRC review (X-energy's Xe-100 had its construction-permit application accepted in 2025), and every one of the 503 units must clear the NRC's design-approval gate under 10 CFR Part 52/50 before concrete is poured.

Strategic Mineral Extraction & Stockpiling Command

National · sovereign reserve vaults, Nevada / Utah
Stalled at: the lawsuits. Rapid, massive mineral extraction triggers environmental litigation and threatens adjacent cultural lands — every deposit near protected habitat forces the program into slow, expensive directional boring from 1.5-mile surface buffer zones, leaving the surface untouched but the schedule in tatters. Jurisdiction: on Nevada and Utah federal land, every deposit needs a plan of operations approved by the Bureau of Land Management (43 CFR 3809, with BLM-led NEPA review), anything near cultural lands triggers National Historic Preservation Act §106 consultation with the State Historic Preservation Offices and affected tribes, and the states add their own mine permits via the Nevada Division of Environmental Protection and the Utah Division of Oil, Gas and Mining.

"Every bottleneck on this page is solvable with money, policy, and persistence. None of them require inventing anything."